Total contract for 3120 cards, delivery schedule of 15.12.06
|
Delivery |
Number of parts |
Date |
|
Pre-series |
120 |
23-Feb-2007 |
|
Series 1 |
500 |
12-Apr-2007 |
|
Series 2 |
500 |
11-May-2007 |
|
Series 3 |
500 |
15-Jun-2007 |
|
Series 4 |
500 |
12-Jul-2007 |
|
Series 5 |
500 |
17-Aug-2007 |
|
Series 6 |
500 |
14-Sep-2007 |
2007
26.2 120 Pre-series delivered
23.4
Repaired HV cards back from ELFAB
30.4
Agreement to launch batch production after solder paste improved
End May 500
ü
End Jun 500
ü
End Jul 500
ü
End Aug 500
ü
End Sep 500
End Oct 500