EE IP5 Responsibilities
Updated detailed EE Installation Sequence
![]() Positions of Dees in CMS |
|
| Height of special plates for EE installation to CMS centre 2200mm | |
| Height of general CMS installation table to CMS centre 2210mm | |
| Main mounting platform general assembly dwg161 pdf dwg | |
| Main mounting platform table dwg162 pdf dwg | |
| Main mounting platform table dwg163 pdf dwg | |
| General view with HE dwg164 pdf dwg | |
| Overview of EE installation 10.2.05 dwg |
Dee Layout Dee photos PHOTOS at 867 - M Droge OPAL transport frames Patch Panels
Crystal and supercrystal locations EDMS drawing files Barcodes for EE
2008
Dee status/faults,
only to 14.10 link
Dee assembly and installation summary:
2.9
HV on both EE+ and EE-
26.8 GUANA events with EE+
elog-3084
elog-3104
23.8 YE- closed
19.8 Full crystal ECAL running in Global with RPC
triggers! (but awaiting HV for EE-)
18.8 EE initial
commissioning completed
Change in duct filling of EE & ES (16),
W Funk 10.6
ppt
Dee support table with respect to HE, A Surkov
14.5 pdf
| SC mounting started | SC mounting completed | SC mounting duration |
OPAL frame | BP cooling system |
DCS on BP |
laser fibres/ PN diodes |
SCs mounted RH quad |
SCs mounted LH quad |
HV cables routed |
Moderator mounted | VPT stability pulser fibres laid |
LV cables installed | Motherboards mapped |
Cooling units mounted | Single tower tests VFE FE LVR | TRLB, data/Trigger fibre routing |
DMEM test |
ESS | N2 pipe, sniffer, rear moderator |
Mount env screen | 867 soak test |
Shipped to P5 | Mounted on HE |
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Dee1 | 28.8.07 | 19.11.07 | 12wks | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | 8.7.08 | 22.7.08 |
| Dee2 | 21.11.07 | 7.2.08 | 11wks | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done |
Done |
Done | Done | Done | Done | Done | Done | 16.7.08 | 25.7.08 |
| Dee3 | 25.2.08 | 10.4.08 | 7wks | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done |
Done |
Done | Done | Done | Done | Done | Done | 24.7.08 | 30.7.08 |
| Dee4 | 22.4.08 | 23.5.08 | 4wks | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done | Done |
Done |
Done | Done | Done | Done | Done | Done | 29.7.08 | 1.8.08 |
Historical record of SC build and SC mounting pdf
2005
Specifications for fittings to connect cooling to the
Dees, J Hill, 29.4 doc
HE cable tray numbering - you will need to zoom to see
the A, B, C, D assignations,
A Surkov, drawn 9 May 2003
pdf
SET OF DRY MOUNT PHOTOS ON HE-,
8 Feb 05
htm
2004
Photogrammetry results of EE+ mounting on HE+, R Goudard 23.9
txt
pdf
SET OF DRY MOUNT PHOTOS ON HE+
htm
Change in duct filling of EE & ES (15), ES/MEM spares, W Funk,
30.07.04
txt
ppt
Dowel pin contract, L Linssen, 10.5
txt
sleeve20.hpg
4.hpg
10.hpg
19.hpg
17.hpg
1.hpg
2.hpg
18.hpg
Flow rates for the flow restrictors on the cooling pipes, W Funk
19.3.04 txt pdf
Change in duct filling of EE & ES (14), W Funk, 02.03.04 txt
ppt
Trigger latency, fibre lengths, W Funk/W Smith/D Barney, 01.03.04 txt
txt2 txt3
txt4 txt5
txt6
Rack layout
in USC55, W Smith 16.2.04 txt
EE ribbon distribution in the ducts and latency problem, W Funk 16.2.04 txt
xls
HV cable lengths, W Funk, 16.2.04 xls
2003
Change in duct filling of EE & ES (13), W Funk, 11.12.03 txt ppt
EE and ES services cable length, estimated costs, problems and
schedules, W Funk 6.10 txt
doc
Corrected and updated Yellow ribbon service count, W Funk 26.9.03 10.20 txt
Removal of some ES services (12), W Funk 23.9.03 comments
ppt
Revised EE duct filling
(10) (4 more LV cables/Q, see
p12), W Funk 7.8.03 ppt
EE and ES numbering and duct filling, W Funk 19.5.03 ppt
Installation talk + mockup photos, CMS week, W Funk 6.3.03 pdf (1.3MB)
2002
YE1 Integration EDR, EE and ES integration, cabling and piping, W Funk 9.Dec pdf
EE and SE Installation, W Funk 11 Sep 2002 ppt
CMS installation review, Sep 2002 doc
EE Installation, EDR-06, 3-4 Sep, 2002, A Surkov pdf
link (to
individual figs)