EE Installation and Commissioning in CMS

New! EE movies New!


PHOTOS

EE IP5 Responsibilities
Updated detailed EE Installation Sequence

Dee Layout and Envelope

 
                            Positions of Dees in CMS
 
Height of special plates for EE installation to CMS centre            2200mm
Height of general CMS installation table to CMS centre              2210mm
Main mounting platform general assembly dwg161 pdf dwg
Main mounting platform table dwg162 pdf dwg
Main mounting platform table dwg163 pdf dwg
General view with HE dwg164 pdf dwg
Overview of EE installation 10.2.05 dwg  

SX and UX installation plans  

Dee Layout    Dee photos   PHOTOS at 867 - M Droge    OPAL transport frames    Patch Panels

Crystal and supercrystal locations    EDMS drawing files    Barcodes for EE

2008
Dee status/faults, only to 14.10  link
Dee assembly and installation summary:
    2.9     HV on both EE+ and EE-
    26.8   GUANA events with EE+    elog-3084   elog-3104
    23.8   YE- closed
    19.8   Full crystal ECAL running in Global with RPC triggers! (but awaiting HV for EE-)
    18.8   EE initial commissioning completed

Change in duct filling of EE & ES (16), W Funk 10.6 ppt
Dee support table with respect to HE, A Surkov 14.5 pdf

2006-8                                                 Assembly, integration and installation history

  SC mounting started SC mounting completed SC mounting
duration
OPAL frame BP
cooling
system
DCS
on
BP
laser
fibres/
PN diodes
SCs mounted
RH quad
SCs mounted
LH quad
HV
cables routed
Moderator mounted VPT stability pulser
fibres laid
LV cables installed Motherboards
mapped
Cooling units mounted Single    tower tests VFE FE LVR TRLB, data/Trigger
fibre routing
DMEM
test
ESS N2 pipe,
sniffer, rear moderator
Mount env screen  867
soak test
Shipped to P5 Mounted
on HE
Dee1 28.8.07 19.11.07 12wks Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done 8.7.08 22.7.08
Dee2 21.11.07 7.2.08 11wks Done Done Done Done Done Done Done Done Done Done Done Done

Done

Done Done Done Done Done Done 16.7.08 25.7.08
Dee3 25.2.08 10.4.08 7wks Done Done Done Done Done Done Done Done Done Done Done Done

Done

Done Done Done Done Done Done 24.7.08 30.7.08
Dee4 22.4.08 23.5.08 4wks Done Done Done Done Done Done Done Done Done Done Done Done

Done

Done Done Done Done Done Done 29.7.08 1.8.08

Historical record of SC build and SC mounting pdf

2005
Specifications for fittings to connect cooling to the Dees, J Hill, 29.4 doc

HE cable tray numbering - you will need to zoom to see the A, B, C, D assignations, A Surkov, drawn 9 May 2003 pdf
SET OF DRY MOUNT PHOTOS ON HE-, 8 Feb 05 htm

2004
Photogrammetry results of EE+ mounting on HE+, R Goudard 23.9 txt pdf
SET OF DRY MOUNT PHOTOS ON HE+  htm

Change in duct filling of EE & ES (15), ES/MEM spares, W Funk, 30.07.04 txt ppt
Dowel pin contract, L Linssen, 10.5 txt sleeve20.hpg 4.hpg 10.hpg 19.hpg 17.hpg 1.hpg 2.hpg 18.hpg
Flow rates for the flow restrictors on the cooling pipes, W Funk 19.3.04 txt pdf
Change in duct filling of EE & ES (14), W Funk, 02.03.04 txt ppt
Trigger latency, fibre lengths, W Funk/W Smith/D Barney, 01.03.04 txt txt2 txt3 txt4 txt5 txt6
Rack layout in USC55, W Smith 16.2.04 txt 
EE ribbon distribution in the ducts and latency problem, W Funk 16.2.04 txt xls
HV cable lengths, W Funk, 16.2.04 xls

2003
Change in duct filling of EE & ES (13), W Funk, 11.12.03 txt ppt
EE and ES services – cable length, estimated costs, problems and schedules, W Funk 6.10 txt doc
Corrected and updated Yellow ribbon service count, W Funk 26.9.03 10.20 txt
Removal of some ES services (12), W Funk 23.9.03 comments ppt
Revised EE duct filling (10) (4 more LV cables/Q, see p12), W Funk 7.8.03 ppt
EE and ES numbering and duct filling, W Funk 19.5.03 ppt
Installation talk + mockup photos, CMS week, W Funk 6.3.03 pdf (1.3MB)


2002
YE1 Integration EDR, EE and ES integration, cabling and piping, W Funk 9.Dec pdf
EE and SE Installation, W Funk 11 Sep 2002 ppt
CMS installation review, Sep 2002 doc
EE Installation, EDR-06, 3-4 Sep, 2002, A Surkov pdf link (to individual figs)